A municipality has commissioned a contractor to mow roadside verges and embankments and to clear waterways following a European tender in 2021. The municipality gives the order for a period of one year, with a maximum of three one-year extensions. The agreement can last until December 31, 2024. In the third year, the project manager emails that the agreement is extended until December 31, 2027. That is three years longer than the original term. The municipal board becomes aware of this email later and terminates the agreement on December 31, 2024. They take over the work after a new tender is issued to a third party.
The contractor is not stopping there; he claims to have invested in € 500.000, – machines. In a lawsuit, the contractor is filing multiple claims, citing, among other things, the extension of the agreement and legitimate trust.
The case in outline
The framework agreement concluded between the municipality and the contractor stipulates that further arrangements must be set out in a written addendum. The parties must remain within the framework of the Public Procurement Act 2012. The municipality may terminate the framework agreement, subject to a period of three months.
The municipality has a City Company. The project managers within the City Company oversee the implementation of the agreements.
At the beginning of 2023, the project manager announced that the municipality wanted to switch to a different mowing method. The contractor stated that they would have to invest in machinery. They would, however, be willing to cooperate with the change, but only if the term of the agreement is extended. The project manager confirmed that the agreement will be extended until December 31, 2027. The contractor will then invest significantly € 500.000, – in new machines.
Later in 2023, the municipal administration becomes aware of the email. The municipal administration states that a new tender must be issued and that only the mowing season 2024 will be completed with the contractor. The work will be tendered again.
Claims by the contractor
The contractor starts a procedure in court. In that procedure, she requests, among other things, confirmation that the agreement has been extended. In case that fails, she requests a declaration that the municipality acted unlawfully because the municipality gave the impression that the agreement would be extended but did not do so. In doing so, she requests an advance payment of € 360.000, – of her damages.
Could the window agreement be extended?
The court concludes that the framework agreement was not extended by the project manager’s email in early 2023.
The tender documents indicate that the agreement may last a maximum of four years. According to the Public Procurement Act 2012, an extension beyond that is a substantial change that requires a new tender.
The framework agreement itself is therefore in line with these requirements. Further arrangements must be made regarding its implementation, and must be set out in an addendum and remain within the framework of procurement law. Extending the agreement until December 31, 2027, does not meet these conditions.
Principle of trust and powers
In applying the principle of trust, the court relies on the administrative review framework of the Administrative Jurisdiction Division (ABRvS). The ABRvS examines whether a commitment has been made, whether that commitment can be attributed to the administrative body, and what the significance of the trust created is.
The court concludes that there is no promise involved:
- The extension until December 31, 2027, was in violation of the law and fell outside the authority of the project manager. It is a substantial change that should have led to a new tender.
- The contractor had a duty of investigation, which they did not fulfill. They are a professional party because they more often submit bids in tenders and are familiar with framework agreements.
- The project manager was not authorized to decide on the private-law transaction (extension). That authority lies with the college, represented by the mayor. The mayor also signed the framework agreement at that time.
- The email on which the contractor relies does not show that the project manager acted on behalf of the municipality. The municipality also did not give the appearance that the project manager had authority. Furthermore, the email does not contain details, such as the new prices. Later documents show that agreement on the prices still had to be reached.
The court thus does not allow the trust fund to take further steps and dismisses the contractor’s claims.
Conclusion
The first step in the principle of trust is whether there is an undertaking. Note that an undertaking is made by the competent authority, or ensure that the competent authority is at least aware of it. If necessary, ask about the authority or conduct research into internal power distribution. Furthermore, a stated undertaking must not violate the law and must meet requirements in a contract, such as a written addendum signed by both parties. Without these elements being met, it is extremely risky to act based on the (alleged) undertaking, for example by incurring costs. That could mean that the costs incurred cannot be recovered.