According to the ruling of the Administrative Jurisdiction Division, it is no longer permissible to offset the nitrogen deposition from agricultural land in the preliminary assessment based on general regulations (such as the zoning plan or the environmental plan) with the nitrogen deposition from a housing project. In such cases, it is also mandatory to apply for a nature permit.
First, I will briefly discuss what is in the sentence It is already decided, and then I will discuss the solutions.
Internal consolidation
When assessing whether the nature permit can still be granted, internal netting can still be used. What is the problem then?
Requirements for internal charging under a nature permit
It must be tested whether the benefits are real and/or the measures will be implemented and double efforts (for another project) will be avoided. In general, it is possible to demonstrate this. The problem is the additionality requirement. The nitrogen deposition from agricultural land must first be used in an over-burdened area to reduce it (so it is assessed whether the measure is not already necessary as a conservation or appropriate measure).
When can the nitrogen deposition from agricultural land be used?
Furthermore, internal offsetting with the nitrogen deposition of agricultural land is no longer always possible. When offsetting internally with a permit derived from general rules on agricultural land use, the effects of that permitted use as agricultural land may be taken into account in the reference situation, unless those lands are structurally no longer in use as agricultural land and cannot be re-taken into use as agricultural land without new nature permits. The point of reference for determining whether the lands are structurally no longer in use as agricultural land is the application for the nature permit or the agreement to transfer the rights of the permitted use or another objectively determinable moment. This will also hinder several projects.
What else is possible?
Is there then nothing more possible? Certainly! However, there must be a plan in place. The government can play a guiding role in this, but in my opinion the province, in this case North Holland, also does not have a plan yet.
Additionality and a plan
Why is this plan important? In the case of additionality, the decision on which conservation and/or appropriate measures are taken does not take place at the level of the individual project, but is beyond the scope of that project. This does not mean that the aspects related to the individual project cannot play a role at all, but it is up to the college to make an assessment regarding this. The Department points out that, when a plan, program or package of measures is presented that explains which conservation and appropriate measures are necessary to implement Article 6, paragraphs 1 and 2, of the Hrl, and is in effect, this can be helpful in assessing whether the additionality requirement has been met.
In short, hopefully the government and the province(s) will work together to develop a plan that meets the requirements.
Lock and questions
If you have any questions about nitrogen and the possibilities and impossibilities of projects, you can ask them to me or to one of my colleagues.
Finally, for the attentive reader of the ruling: I do not have an office in Hoorn, but in Alkmaar, and although my first name is Ilse, my initials are E.C.W.
Would you like to read the full statement? You can find it here. here.
Related Blogs
The Impact of the Rendac Decision on Internal Remuneration Interesting ruling: ‘Didam-II’: Supreme Court rules in appeal procedure Circular construction in the Environmental Code: a sustainable revolution? Fixed-term rental contracts law, what does it mean for you? Hit by a agricultural vehicle, entitled to compensation?