The case between Sugar City Investments B.V. (SCI), the municipality of Haarlemmermeer and Neptune Amsterdam B.V.
Background to the case
Due to subsidence, damage was caused to the municipal building of the municipality of Haarlemmermeer in Halfweg. This damage occurred after a large amount of granulate (crushed rubble, 11 million kilograms) was dumped just behind that building, at a distance of 7 to 10 meters from the building. This created a mound of granulate.
According to the municipality, this landfill is the cause of the subsidence and it sued SCI for damages. SCI, in turn, tried to hold Neptune liable and claimed exemption from any claims for damages from the municipality. Neptune argued that SCI had designated the location for the landfill and was therefore responsible for the consequences thereof.
Judgment of the court
In the first instance, the court ruled that SCI was liable for the damage to the town hall, and that SCI had to compensate for the damage by making a detailed assessment of it to the state. SCI’s claims of immunity against Neptune were rejected.
The court found that:
- SCI was responsible for the method of carrying out the landfill and the resulting landfill area.
- SCI should have verified the required geotechnical knowledge, including the bearing capacity of the ground.
- Any science of Neptune about the inadequacy of the location could not remove the liability of SCI.
Higher appeal
The court upholds the court's verdict. In the arrest The court finds that the causal link between the deposit of the granulate and the damage to the town hall was sufficiently demonstrated by various expert reports.
According to the court, SCI had a duty of care They should have also considered whether the deposit of the granulate would cause damage to the town hall. Even if Neptune had designated the location where the granulate was deposited, that would not absolve SCI of its own responsibility.
The argument of SCI that they did not possess the knowledge of the load-bearing capacity of the ground when they loaded the ground next to the town hall does not hold up either. The court finds that it was foreseeable – at least it should have been so – that damage could occur for SCI, due to the enormous weight of the granular material, the limited size of the storage location and the proximity of the town hall. SCI should have ascertained beforehand the load-bearing capacity of the ground, for example by obtaining information from Neptune. Furthermore, SCI has not demonstrated that it had no knowledge of the load-bearing capacity of the ground.
The indemnification claims of SCI against Neptune were also rejected on appeal. This was also taken into account that the agreement between SCI and Neptune specifically stipulated that SCI would indemnify Neptune for damages resulting from the granules and their storage. Neptune could therefore rely on the fact that any damages would be borne by SCI.
Self-care responsibility
The court confirms that a party that carries out work near vulnerable third-party properties has a duty of care. That party cannot simply follow the instructions of its client. As a party, you must independently assess whether the action may cause damage. Even if another party provides instructions, they must not simply follow them without independently assessing the risks.
The duty of care and the duty of investigation cannot be transferred contractually or factually to the client. Contractual agreements regarding indemnification must be interpreted carefully, and in this case they cannot limit liability towards third parties.
Do you have questions about damage and liability in construction projects? Then contact one of our lawyers.
Related Blogs
The payment of your advance payment for personal injury remains outstanding, what now? Personal injury and a liability insurance for occupants (SVI) Hit by a agricultural vehicle, entitled to compensation? Personal injury suffered during an internship: who is liable? Bitten or attacked by a dog – who pays for the damage?