Introduction
On September 24, 2025, the Council of State issued a ruling regarding the nature permit of SABIC Innovative Plastics BV (hereinafter: “SABIC”) in Bergen op Zoom. This ruling not only puts SABIC’s permit in jeopardy, but also has far-reaching consequences for companies operating near Natura 2000 areas. What exactly has been decided, and what does this mean for companies that want to expand or become more sustainable? And what consequences does the ruling regarding museum Voorlinden, which was also issued on September 24 last year and where the nature permit also failed, have?
The case in brief
SABIC, a major petrochemical company, applied for a nature permit for the construction of a wood-fired biomass plant (hereinafter: ”bmi”) and a hot oil stove. These installations had to replace the existing installation. The North Brabant Provincial Council granted the permit, but environmental organizations BMF and MOB objected. They found that the consequences for nature had not been sufficiently examined and that the permit had not been granted on the correct grounds. In the case of museum Voorlinden, it was a nature permit for a parking lot.
Key points from the ruling
1. What is a project?
The first question was whether there was a single project. The Administrative Jurisdiction Division of the Council of State (hereinafter: the Council of State) ruled, contrary to the court, that the BMI and the hot oil boiler should be considered as one part of the SABIC project. The installations are physically and functionally connected to the rest of the company and are necessary for production purposes and serve to replace the current installation. There is also no spatial separation. The fact that part of the steam is supplied to third parties does not affect this. The majority of the steam is used for the own installation.
On September 24, the Council of State also ruled in another case, concerning museum Voorlinden, that the appropriate assessment should not only consider the modification of the project, but the entire project.
Read here the entire statement.
2. Course for internal reconciliation
One of the biggest changes is the way internal charging is assessed. For the rulings of December 18, 2024, companies were able to compare the consequences of a new project with an existing permitted situation (the reference situation). See also my interview with Flevoland Broadcasting. It does follow from this judgment that it is not inconsistent to derive a reference situation from a nature permit that does not have a sufficient and appropriate assessment underlying it.
The Chamber follows the arguments of the environmental organizations BMF and MOB that it is not in accordance with European law or the principle of Union loyalty to derive a reference situation from an insufficiently assessed nature permit. The court rightly reached this conclusion as well. In short: In the preliminary assessment, only the new project itself can be taken into account. Internal offsetting can only be used as a mitigating measure in the appropriate assessment. This means that companies can no longer automatically assume their existing emission capacity. In light of this, the reference situation was incorrectly included in the nature permit of May 18, 2022 when determining whether significant consequences have been excluded beforehand based on objective data.
In the case of museum Voorlinden, the Council of State determined that if the reference situation is taken into account in the appropriate assessment, it must be determined whether the additionality requirement is met. In that case, that was wrongly not done.
3. What is the reference situation?
As stated in the December 18 ruling, the reference situation is derived from the nature permit for the permitted project on the site where the intended activity is planned. The reference situation is derived from the environmental permit that was in effect on the reference date, which is the moment when Article 6 of the Hrl became applicable to the relevant Natura 2000 site. If, after the reference situation, an environmental permit is granted for an activity with fewer consequences for Natura 2000 areas than the activity permitted on the reference date, the reference situation is derived from that later permit. A reference situation cannot be derived from a nature permit or environmental permit that has expired or expired.
In this case, the 2016 nature permit means an irrevocable permit that may be used as a reference situation, unless it has expired or lapsed. The latter has not been proven.
However, the content of the permit itself is also taken into account. The maximum emissions listed in the 2016 permit for nature protection determine the maximum emission level of the project. It is therefore important to assess what exactly is included in the environmental permit. It is also important to note that the nature protection permit cannot limit the maximum deposit amount, as this is not possible in a nature protection permit.
3. More stringent requirements for environmental measures
SABIC and the municipality assumed that only clean biomass would be used, thereby limiting the emissions of harmful substances. However, the Department finds that this is not adequately documented in the permit. The use of clean biomass must be explicitly guaranteed, or the calculations must be adjusted. This forces companies to concretely and in a verifiable manner document their environmental measures.
4. Transition phase not well organized
The transition from the old to the new installations was not properly regulated in the permit. As soon as the new installations are completed, the old permit expires and the Cogen2 installation may no longer be used. This means that the intended test phase and the temporary simultaneous use of both installations are not permitted.
Consequences for SABIC and the industry
The ruling means that SABIC and the College of Deputies must take a new decision regarding the permit. In doing so, they must:
- Consider the BMI and the hot oil plant as one project with the other activities and facilities of SABIC;
- The use of clean biomass is explicitly guaranteed in the permit;
- Internally reconcile only when applying mitigating measures in the appropriate assessment and not in the preliminary review;
- The consequences of the irrevocable nature permit from 2016 may, under certain conditions, be taken into account as a mitigating measure in the appropriate assessment, taking into account that the emission from the project authorized at that time has been maximized in this permit.
- Clarify the transition phase between old and new installations.
For companies, this ruling means that the permit process for expansion or sustainability projects will become stricter and more transparent.
Conclusion
It is important to consider what exactly is included in a nature permit. The ruling is therefore relevant not only for SABIC, but for all companies operating near Natura 2000 areas.
Would you like to learn more about this ruling or the consequences for your company? Then contact one of our specialists.
Related Blogs
Withdrawal unused space nature permit Refusal and rejection requests for revocation of nature permits Internal consolidation with general rules is no longer allowed. What solutions are possible? The Impact of the Rendac Decision on Internal Remuneration Freelancers, please note! Important change as of January 1, 2025: lifting of the enforcement moratorium